The main issues at the moment are that the electrics are not yet in place and connected to the grid... and as a knock on effect, the solar is not fully installed, panels are up but the inverter and batteries are not in place yet....There's also a complication in that the power load in the kitchen was not properly set up to handle 3 ovens... despite me telling the spark we had 3 ovens and him even repositioning the sockets behind the ovens to make plugging them in easier... but all 3 socket were on a single circuit with a 16amp breaker... each oven take 12-15amps...ermmm yeah that was a strange mistake for an experienced spark to make. A hasty rewire has been arranged to add 3 circuits to handle them.
Plumbing is also stalled, mainly due to some missing mixer taps. We changed our spec several months ago to add a hot water boiler to feed the 3 bathrooms on the right, (east/west...no idea) side of the house, so instead of a single cold feed they now have hot and cold but for whatever reasons, no one prompted us to choose new taps to handle the dual water flow....And there's been a slightly mad delay in getting those taps sorted resulting in a freeze on the plumbing work. Also hot water heaters for the guest room shower, were not in our contract, but again no one actually pointed it out.
Granite tops are also slightly delayed... won't be ready until Tuesday...hmmm means we can't really use the kitchen properly for a few days, but again... not really a biggie but annoying that we get told today, and not last Friday...cos we ordered it 3 or 4 Fridays ago.
Windows however, and the bedroom/balcony door are replacement in progress and looking 100% better than the cheap crap that was there before...Furniture is mostly in place, though still waiting some wardrobes and sideboards for the guest rooms... We fitted Index Wardrobes in the master bedroom...the fit isn't exact sadly, but it's close enough for jazz. We do still need to buy a coffee table, and a load of bedding.
Jobs still to do.
Fit cooker hood,
Kitchen backsplash tiles.
Fix PEA reported issues to allow us to get meter. (and the knock on, of solar, but that's not the builders issue)
Rewire power and install ovens.
Final outdoor clean down and painting
Seal and install locks on some windows.
Glaze the front window.
Fix PEA reported issues to allow us to get meter. (and the knock on, of solar, but that's not the builders issue)
Rewire power and install ovens.
Final outdoor clean down and painting
Seal and install locks on some windows.
Glaze the front window.
Several water faucets to be fitted to blue pipes (for example the washing machine point)
Change handle on front gate (which we really don't like and will point out during handover)
Install boiler/bath and bathroom sinks and a granite sink top in the master.(next Tuesday...grrr)
Finish spreading subsoil to level the ground
Fit heater to guest shower
Fit heater to kitchen sink
Install grease trap (and presumably sink?) may be delayed until the counter top is in place and sink installed. (which by the way I have not seen yet...)
Only today and tomorrow left to do these jobs.......though I can't hold them responsible for things delayed by granite... So overall I'm not confident, though I would not be surprised if the worker numbers double today and tomorrow to get these things done.
Hand over is scheduled on the 31st, which of course gives me a chance to point out issues, then they can
deal with snag list which already has a few issues like a light switch not working and some slightly wonky tiles on the kitchen counter.
We can also point out any other issues that might crop up for a year after handover.. so we're covered for any big or small issues.
On the plus side, we don't move out of the rental until the 18th, so if we need to stay here a few more days that's not a problem, we're not being chased down the street.. We will do a slow gentle transition..
Then stage 2 begins... Jirawan gets to design her fantasy Garden
Stage 3... Thai Kitchen, Laundry point and Patio..... Again Jirawan gets to have her choice of Thai kitchen, I'll help with sorting out the patio.
Phew, I have missed out some things for sure but that's where we are.... as far as I can remember
Ahthankyew
Change handle on front gate (which we really don't like and will point out during handover)
Install boiler/bath and bathroom sinks and a granite sink top in the master.(next Tuesday...grrr)
Finish spreading subsoil to level the ground
Fit heater to guest shower
Fit heater to kitchen sink
Install grease trap (and presumably sink?) may be delayed until the counter top is in place and sink installed. (which by the way I have not seen yet...)
Only today and tomorrow left to do these jobs.......though I can't hold them responsible for things delayed by granite... So overall I'm not confident, though I would not be surprised if the worker numbers double today and tomorrow to get these things done.
Hand over is scheduled on the 31st, which of course gives me a chance to point out issues, then they can
deal with snag list which already has a few issues like a light switch not working and some slightly wonky tiles on the kitchen counter.
We can also point out any other issues that might crop up for a year after handover.. so we're covered for any big or small issues.
On the plus side, we don't move out of the rental until the 18th, so if we need to stay here a few more days that's not a problem, we're not being chased down the street.. We will do a slow gentle transition..
Then stage 2 begins... Jirawan gets to design her fantasy Garden
Stage 3... Thai Kitchen, Laundry point and Patio..... Again Jirawan gets to have her choice of Thai kitchen, I'll help with sorting out the patio.
Phew, I have missed out some things for sure but that's where we are.... as far as I can remember
Ahthankyew
